8/18/03-8/22/03 Restoration of NG1 and additions to AND/R
Ladder racks, motor cables, and detector cables are installed in the trench on top of the electrical power and air lines.
The control station for the NG1 reflectometer was set up in its new location...
and
... the cables were re-routed to the front, through new ladder racks, to the electronics racks.
"No Entry" signs are mounted above the neutron beam paths for both NG1 and AND/R and the AND/R shutter control switch is mounted to the beam stop (not shown).
The NG1 shutter control / safety system is re-wired for it's new configuration
Slit #1 is installed just downstream of the monochromator inside the shielding.